Objectives
- Permanently abandon 4 suspended wells in the Central North Sea.
Method
- Reviewed Well Status.
- Defined P&A strategy and outlined rigless options
- Prepared and submitted Regulatory and Environmental Permits
- Developed P&A Programmes
- Placement of P&A Contractor contract
- Developed plan for setting deep set cement plug
- Management of P&A Operations
- Submitted post P&A Reports
Challenges
- Identifying a suitable vessel
- Limited timeframe to plan prior to Operations
- Setting cement plugs at 2500ft with SWAT tool
- Abandoning 1 legacy well with limited well data
Outcomes
- All 4 wells P&A within AFE
- Over 43,000 man hours with zero accidents, incidents or environmental spills
- Seabed cleared of all well equipment
- License holder obligations met