Zenith Energy were tasked with delivering well plug and abandonment engineering support across wells, completion and subsea/well systems disciplines for 9 x SS development wells.

Result:

  • All wells permanently abandoned in compliance with UK Oil & Gas Abandonment Guidelines
  • Well operations delivered 12 days ahead and £1.7MM under AFE
  • Application of new technology
  • Detailed Lessons Learned database collated and applied to subsequent operations